I want to know the specific start and end dates and times when setting the aggregation period from 1 to 12 months.
Explain the starting point and ending point
Starting point
This is the date ● months before the date the evaluation is executed. The time is the same as that set in “Evaluation execution timingˮ
*If there is no date exactly ● months ago, such as in leap years or on the 31st of the month, the date will be the closest pervious date.
Ending point
It will be 1 second before the evaluation is executed.
Example
Evaluation execution schedule | Starting point of aggregation period | Ending point of the aggregation
period | |
Execute the evaluation at 00:00
everyday for the past 1 month. | March 1, 2023 0:00 | February 1, 2023 0:00 | February 28, 2023 23:59 |
Execute the evaluation at 00:00 everyday for the past 1 month.
(No corresponding same date in the
previous month) | March 31, 2023 0:00 | February 28, 2023 0:00 | March 30, 2023 23:59 |
Execute the evaluation at 22:00 everyday for the past 3 months | May 29, 2023 22:00 | April 29, 2023 22:00 | May 29, 2023 21:59 |
Execute the evaluation on the 1st day
of each month for the past 1 month. | July 1, 2023 0:00 | June 1, 2023 0:00 | June 30, 2023 23:59 |
Did this answer your question?
😞
😐
🤩
Last updated on July 31, 2024